Cataby Drop Out Dam Bulk Earthworks & Pipework
Bulk earthworks were completed, including 1,381 m³ of cut and 4,017 m³ of fill. Detailed earthworks, such as anchor trenching and battered slopes, were executed in strict accordance with contract specifications. The existing spillway on the Turkeys Nest was removed, and a new spillway was constructed connecting the new Drop Out Dam to the existing Turkeys Nest. Additionally, a Franna access ramp and emergency access works were constructed to support safe site operations.
Location
Cataby, WA
Duration
July 2023 - October 2023