HPGR Expansion Concrete Install, Sino Iron Project

The project included the provision of supervision, labour, materials, plant, and equipment to complete 2,980 m³ of concrete for the HPGR Expansion Project. This encompassed detailed earthworks, including rock excavation, cut and fill, backfill, conditioning, and compaction. The scope also involved the supply and installation of reinforcement, formwork, cast-ins, concrete, curing materials, power tools, and consumables. Formwork, reinforcement, and concrete pours were successfully completed for the HPGR, Pebble Crusher, Screening Plant, and Transfer Station.

Location

Karratha, WA

Duration

October 2022 - July 2023


Project Gallery

Australia's leading civil, concrete, and formwork specialists.  With decades of experience in the construction industry, we strive to deliver quality results in a timely and cost-effective manner.

Connect:

Phone: (08) 6246 5333

Email: admin@glenviewconstruction.com.au

Address: Level 4, 200 Adelaide Terrace, East Perth WA 6004

Office hours: 8:00 AM - 4:00 PM

  • LinkedIn

© 2024 Glenview Construction Pty Ltd.

bottom of page