HPGR Expansion Concrete Install, Sino Iron Project
The project included the provision of supervision, labour, materials, plant, and equipment to complete 2,980 m³ of concrete for the HPGR Expansion Project. This encompassed detailed earthworks, including rock excavation, cut and fill, backfill, conditioning, and compaction. The scope also involved the supply and installation of reinforcement, formwork, cast-ins, concrete, curing materials, power tools, and consumables. Formwork, reinforcement, and concrete pours were successfully completed for the HPGR, Pebble Crusher, Screening Plant, and Transfer Station.
Location
Karratha, WA
Duration
October 2022 - July 2023